Acwa Power selected as preferred bidder for Red Sea utilities PPP scheme

16 Sep 2020
Acwa Power selected as preferred bidder for Red Sea utilities PPP scheme

Two consortiums had submitted best and final offers on 31 August for public-private partnership (PPP) contract on the multibillion-dollar Red Sea Tourism Development project in Saudi Arabia.

The Red Sea Development Company (TRSDC) has selected a consortium led by the local Acwa Power as the preferred bidder for the planned public-private partnership (PPP) utilities project in Saudi Arabia.

Acwa Power, in consortium with Energy China, submitted a best and final offer (BAFO) on 31 August along with the other bidding consortium, led by UAE’s Masdar and France’s Engie. Both groups had submitted original proposals on 10 May.

According to sources close to the scheme, the Acwa Power consortium has been selected as preferred bidder for the multi-faceted utilities PPP contract.

The PPP contract will include the provision of power and water production, sewage treatment and solid waste treatment. The Red Sea Development Company is owned by sovereign wealth vehicle Public Investment Fund (PIF), and the PIF will provide the guarantee for the 25-year offtake agreement.

Under the first phase of the Red Sea development, which is due to be commissioned in 2022, power generation capacity will be required to service a peak demand of 210MW. Power is planned to be generated for the first phase from photovoltaic (PV) solar, wind energy, energy storage batteries and biofuel emergency power.

Under the second phase, which is due to be commissioned by 2030, power generation capacity will be required to meet peak demand of 360MW. The client is planning for geothermal and concentrated solar power (CSP) to add additional capacity by 2030.

For water production, two seawater reverse osmosis (SWRO) plants will be developed with a capacity of 30,000 cubic metres a day (cm/d) under the first phase. The demand will be split between potable water, 21,000 cm/d, and irrigation top-up, 9,000 cm/d.

Under the second phase, an additional SWRO plant will be developed in addition to brine squeezer and chlor-alkali technologies to meet expected demand of up to 50,000 cm/d, split 39,000cm/d and 11,000cm/d between potable water and irrigation top-up respectively.

The selected developer will also be required to provide a sewage treatment plant (STP) with a capacity to treat up to 18,000 cm/d of sewage under the first phase of the project through a constructed wetlands scheme. The peak sewage flow of the development is expected to reach 34,000 cm/d by 2030.

For the waste treatment development, the PPP contract will cover collection, automatic recovery and waste-to-energy production for up to 30 tonnes per day (t/d) under the first day. This will rise to 55 t/d by 2030,

TRSDC was established in line with the kingdom’s Vision 2030 economic reform plan to diversify the country’s economy and increase the kingdom’s tourism sector.

Under the first phase development, TRSDC is planning to develop five islands, two inland sites and deliver 3,000 hotel keys to accommodate 300,000 visitors a year by 2022. By 2030, the client hopes to have developed 22 islands, six inland sites and have delivered 8,000 hotel rooms to service up to 1 million visitors a year.

Energy & Utilities - Middle East and Africa Market Outlook Report 2024.

This must-have report for industry players offers a thorough understanding of the latest developments, challenges, and opportunities in the region, supported by data, analysis, and expert insights. 

E&U Podcast

Subscribe to our Market Talk podcast for the latest on the key issues and trends in the energy and utilities sector

List your business

Create a business listing on the Energy & Utilities markeplace

Sign up for the FREE Energy newsletter

The latest news and analysis sent to your inbox.

Drop Us A Message
I have read, understood and consent to your Privacy Policy